Construction Updates
We’re proud to share that the perfect place to build your dream home is taking shape before your eyes.
Under Construction
Stage 1A
Est. Titles Due
Q2 2026
Est. Settlement Due
Q3 2026
Works90%
Site EstablishmentJun-25
Bulk EarthworksJul-25
Sewer ReticulationSep-25
DrainageNov-25
Water ReticulationJan-26
Subgrade Placement WorksFeb-26
Electrical and NBNMar-26
Footpaths/ Ashpalt/ Line MarkingApr-26
Practical CompletionMay-26
Registration
Statement of ComplianceJun-26
Lodge Plan of SubdivisionJun-26
Estimated TitlesJul-26
Estimated SettlementsJul-26
Stage 1B
Est. Titles Due
Q2 2026
Est. Settlement Due
Q3 2026
Works90%
Site EstablishmentJun-25
Bulk EarthworksJul-25
Sewer ReticulationSep-25
DrainageNov-25
Water ReticulationJan-26
Subgrade Placement WorksFeb-26
Electrical and NBNMar-26
Footpaths/ Ashpalt/ Line MarkingApr-26
Practical CompletionMay-26
Registration
Statement of ComplianceJun-26
Lodge Plan of SubdivisionJun-26
Estimated TitlesJul-26
Estimated SettlementsJul-26
Stage 1C
Est. Titles Due
Q3 2026
Est. Settlement Due
Q3 2026
Works90%
Site EstablishmentJun-25
Bulk EarthworksJul-25
Sewer ReticulationSep-25
DrainageNov-25
Water ReticulationJan-26
Subgrade Placement WorksFeb-26
Electrical and NBNMar-26
Footpaths/ Ashpalt/ Line MarkingApr-26
Practical CompletionMay-26
Registration
Statement of ComplianceJun-26
Lodge Plan of SubdivisionJun-26
Estimated TitlesJul-26
Estimated SettlementsJul-26
Stage 1A
Works90% Site EstablishmentJun-25 Bulk EarthworksJul-25 Sewer ReticulationSep-25 DrainageNov-25 Water ReticulationJan-26 Subgrade Placement WorksFeb-26 Electrical and NBNMar-26 Footpaths/ Ashpalt/ Line MarkingApr-26 Practical CompletionMay-26 Registration Statement of ComplianceJun-26 Lodge Plan of SubdivisionJun-26 Estimated TitlesJul-26 Estimated SettlementsJul-26
Stage 1B
Works90% Site EstablishmentJun-25 Bulk EarthworksJul-25 Sewer ReticulationSep-25 DrainageNov-25 Water ReticulationJan-26 Subgrade Placement WorksFeb-26 Electrical and NBNMar-26 Footpaths/ Ashpalt/ Line MarkingApr-26 Practical CompletionMay-26 Registration Statement of ComplianceJun-26 Lodge Plan of SubdivisionJun-26 Estimated TitlesJul-26 Estimated SettlementsJul-26
Stage 1C
Works90% Site EstablishmentJun-25 Bulk EarthworksJul-25 Sewer ReticulationSep-25 DrainageNov-25 Water ReticulationJan-26 Subgrade Placement WorksFeb-26 Electrical and NBNMar-26 Footpaths/ Ashpalt/ Line MarkingApr-26 Practical CompletionMay-26 Registration Statement of ComplianceJun-26 Lodge Plan of SubdivisionJun-26 Estimated TitlesJul-26 Estimated SettlementsJul-26